Christmas and Electrification Rail News
Paddington Station will be closed during the Christmas to New Year Period. Mark Hopwood, GWR’s Managing Director, advises:
“I thought Henley branch users would want to have early notice of planned works over Christmas this year.
Full details are on our website https://www.gwr.com/travel-updates/christmas-2016 but the key thing to note is that London Paddington will be closed to all rail services from Saturday 24 December to Thursday 29 December.
This will mean GWR rail services starting and finishing at Ealing Broadway, where customers can make a connection to the underground, or scheduled bus services for travel into London.
In addition, no trains will call at Acton Main Line and Hanwell from 24 December to 1 January or the Greenford branch from 24 December to 2 January. Tickets will be valid on scheduled London Bus or TfL Underground services.
The Marlow line will close from 24 December to 2 January, and trains will also not call at Burnham or Taplow. We will provide replacement bus services for Burnham, Taplow and the branch line.
Anything you can do to help us spread the message about the changes would be very much appreciated. The link gives information on specific lines and if you are able to share it more widely we would be grateful.
I am also happy to provide more information to should you need it on this, or indeed on any other aspect of our services.”
On electrification plans for the main line and branch line, Network Rail advise that:
- The branch line will get single track cantilever electrification, rather subtler than the big mainline gantries.
- Unlike at Maidenhead, the station canopies at Henley and Twyford will not need major adjustment.
- The new electric trains already running between Hayes and Paddington might be expected to run to Maidenhead by June 2017 and Reading by 2017.
- The Henley branch could expect to be running electric trains within two years of approval to start work.
GWR advise that the through services from Henley to London and back may stop when the electric train service from Paddington to Reading starts, since capacity is potentially greater on the new trains.
Remember that while this will then require a change at Twyford at all times, it also means the branch shuttle can continue to run rather than all the rolling stock disappearing to London. This has the potential to enable additional morning rush hour services out of Henley and a more reliable evening schedule on the branch which won’t be (in itself) at risk from disruption between Paddington and Twyford. GWR still hope to run a fast half hourly peak connection via Twyford in due course rather than the fast/slow arrangement currently in place.
It is still proposed that daytime off-peak services into Shiplake and Henley will be half-hourly instead of every 45 minutes from May 2017. If you support or have other views on this proposal please advise henleytrains@gmail.com to ensure they are heard.
Henley Trains are happy to help with Henley rail queries at any time.