Red Lion Hotel Owners Working With Conservation Officers on Planning Application
The listed building planning application to refurbish the Red Lion Hotel has been submitted to South Oxfordshire District Council and was discussed at last night’s Town Council Planning Committee.
The Grade II listed hotel was bought by Grace Leo in conjunction with Singapore-based shipping entrepreneur and hotel investor, Tim Hartnoll in October 2020 from MG Hotels. With a £3m investment for refurbishment they hope to reopen the hotel in July 2021 with a new name Relais Henley after the French word meaning “coaching inn”.
The internal refurbishment of the hotel will include new internal decoration and renewal of servicing to guestroom areas as well as limited internal alterations to specific ground floor sections of the building (the Regatta Restaurant and approach corridor) to reinstate previous larger spaces.
The public areas will also be redecorated, generally on a like for like basis. Strip out works to facilitate the design of the refurbishment have been undertaken in agreement with planning/conservation officers.
A guestroom which was recently constructed within the roof space of the Regatta Room will be removed to reinstate the restaurant’s original internal double height volume. The Regatta Room will be converted into the new restaurant with an open deck out to the courtyard at the rear.
There are seven existing guestrooms located around the hotel courtyard which are not listed. These rooms will be converted to provide six new guestrooms, including the three statutorily required fully accessible guestrooms. One of these rooms will be created within an existing external store.
Four new guestrooms will be created on the north section of the ground floor of the Red Lion Stables. This area is currently derelict, in a state of very
poor repair and being used for storage.
The loft of the Red Lion Stables will be converted to four new guestrooms which were previously given consent in 2012. The hotel will therefore go from the current 35 rooms to 37 rooms.
The current guest lounge will become a guest bar, serviced from the hotel lobby. The current bar, positioned to the right of the hotel entrance, will become a small deli accessible to both hotel guests and drop in visitors.
The rear non-structural partition wall of the current reception area will be removed to restore the original plan area of the reception – as it has been established by the statement of heritage significance. A recent cottage-paned glazed non-structural partition between the reception lobby and the bar will be removed to improve the physical connection between the two spaces.
Grace Leo is working with Conservation and Design Officers at SODC. Rob Workman Conservation and Design Officer has put a holding objection on the planning application until amended plans and additional information have been provided. In his report he states:
Proposed Air Con Installation
Further opening up/investigative work to floors should be undertaken to expose routes now proposed. I have asked that Dr Kathryn Davies, heritage consultant, should review historic fabric within these voids and provide an addendum to heritage impact assessment covering installation of additional services to progress.
Charles I Wall Painting
Following advice from Dr Kathryn Davies a specialist wall painting conservator will be assessing the historic wall painting depicting Charles I coat of arms in room 108 to provide advice on any preservative measures required. Further discussion to be had once this has been undertaken.
Dendro-dating Historic Timber
It was also agreed that dendro-dating would be undertaken to inform historic development of building and assist with heritage appraisal and impact
assessment (HIA).
Historic Lath and Plaster Ceilings
Any areas of historic lath and plaster should be repaired like for like and impervious plaster/paints avoided where this is specified. Where historic
ceilings have failed substantially as laths have been fixed too close as inspected onsite these areas should be carefully taken down and replaced like
for like but further advice should be taken form a specialist in lime plastering before specifying and embarking on such works.
Conversion of Stores/Stable Block
Agreed with the agent onsite that a schedule of works/specification of materials for conversion element should be provided upfront or by appropriate
condition. This conversion work should utilise vapour permeable materials as relevant Historic England Advice notes and works will also need to meet current building control but not use harmful impervious materials.
External Works/Signage
The external alteration works including alterations to signage will be subject of a second application for listed building consent. The existing signage has been stored safely on site for appraisal and refurbishment. Proposals will be submitted in due course but at this stage I consider the name ‘Red Lion Hotel’
should remain on the building in some form along with the terracotta lion and urns above the portico entrance.
To see the full application details click here