Three More Pedestrian Crossings Proposed
Three further pedestrian crossings have been proposed to be installed on Bell Street near Rupert House School and two on Kings Road, one at the junction of West Street and one at the bottom at Northfield End.
At the Town Council’s Planning Meeting last week, Councillors reviewed a report which included a traffic survey that was completed at five locations in May 2022 (the above three plus before the Kings Road roundabout near to Mount View junction and the Fairmile opposite Bowling Court). Traffic speed and volume counts, together with pedestrian counts were carried out. The highest number of pedestrian counts was the upper end of Kings Road crossing to West Street with 676 crossings in one day.
The Councillors recommended to allocate £15,000 from Community Infrastructure Levy for the design work for the three crossings. It was proposed that a light-controlled pelican crossing would be installed on Bell Street and a zebra crossing at the Northfield End of Kings Road. It is not possible to install a zebra crossing at the Kings Road/West Street junction due to the narrow footways. However, it was suggested that a raised table with different coloured surface and give way markings could be installed at the junction. This would highlight that pedestrians have priority.
The cost of the three crossings would total £223K exc design work if they all went ahead. These costs would also be taken from CIL given to the Council from new housing developments. Henley Town Council currently has an unallocated CIL balance of £121,957 and is expecting more over the next year.
The pavement work has been completed for the Swiss Farm crossing on the Marlow Road and is now waiting for the pelican light installation to be completed.





That’s £75k per crossing, OUTRAGEOUS COST!!!…. but all 3 are desperately needed and thankfully paid for by funds from developments. How long has Henley been waiting for the Marlow Road one to be completed?? it’s like watching paint dry.
According to Stefan, company doing the puffin crossing electrical installation are busy but the work will be done at the end of July. I agree it is taking ta long time, but having lived here for nearly 10 years I am used to slow process with most things connected with the three local councils.