Bridge Works Due to Start But River Levels and Sourcing of Stone May Delay This
Repair and cleaning works to the stonework of Henley Bridge and removal of the H graffiti were due to be started on Monday 14 October by Oxfordshire County Council contractors.
Calls for repairs to the historic Grade I listed bridge built in 1786 have been campaigned for many years after numerous boats have hit the stonework. One incident in 2018 saw a boat (photo below) take out a large piece from one of the arch covings.
The work will include the removal of vegetation which is growing form mortar joints; reface stones on northern and southern elevations where there is severe deterioration; repoint with an appropriate hydraulic lime based mortar; install hidden slate reinforcement behind stones for extra stability; remove vegetation on the south western wing wall; remove vegetation on the north eastern bridge deck wall; undertake repairs to the balustrade where there are cracks and chips; replace the few balusters that are severely eroded; and remove insensitive adhesive material that was used on a previous lighting scheme (the cabling was already removed).
The Environment Agency have issued a river restrictions notice for the works – Boats using the river will have to navigate through different arches during the work. Between Monday 14 October and 23 October the centre arch will be closed to all traffic, the two arches on the Remenham, Wokingham east, left side of the river will be closed between 24 October and 5 November and the two arches on the Henley, Oxfordshire west, right side of the river will be closed between 6 and 22 November.”
The H graffiti was sprayed on in May 2022 and after two years Oxfordshire County Council said that planning permission was required to complete this work.
A spokesperson for Oxfordshire County Council said, “We intend to carry out the graffiti removal as part of the stonework works. It is currently unclear when the stonework repairs will start on site due to a couple of issues.
“The recent heavy rainfall has raised river levels and flows, so that it is not currently safe to access the river to begin the repairs. River levels are being monitored, but there is a significant risk that this will delay the start of the work.
“The subcontractor has encountered problems in sourcing the particular quarried stone that the Conservation Officer for Listed Building consent has approved. It appears that there is a 6 to 8 week lead time to obtain this particular stone type, and the subcontractor is exploring alternative options.”
OCC have also confirmed that the replacement of the York paving, which is associated with a utility company reinstatement, does not form part of these proposed works which were removed in July 2021!