Town Council Have No Power Over Telecoms Mast Installation at Makins
A planning application has now been submitted to install a 20 metre 5G mast with cabinet, antennas and dishes on Makins Recreation Ground by EE despite the land being owned by Henley Town Council who rejected the initial proposed installation.
At the Full Council meeting last night Cllr David Eggleton and other Gainsborough residents who back on to Makins Recreation Ground attended the meeting to raise concerns about the proposed 5G mast. They asked why Freemans Meadow and other spaces had been rejected as a site for the 5G mast; why certain residents and users of the recreation ground had not been notified; and why biodiversity (affect on wildlife and insects) had not been taken into consideration. Concerns were also raised about the potential health effects from the mast.
Only immediate neighbours on Gainsborough Hill, Deanacre, Haywards and Harcourt Close were advised of the consultation by SODC. On the planning portal, only the SODC Forestry Officer and Contaminated Land team are listed as respondees. There is no SODC Ecology Officer listed.
Charlotte Wolfe, a resident who spoke at the meeting has started a petition detailing the concerns. She also adds, “The land was gifted to our town for the purposes of recreation and I am worried this sets a precedent for further development. It’s unnecessary to build the mast there and the application is not sound or convincing.” The petition can be found at https://chng.it/gNR7T7QwYb
Town Clerk, Sheridan Jacklin-Edwards clarified at the meeting that it was EE that had proposed to install the mast, not the Town Council; that the Town Council had attempted to reject the proposals but had received legal advice that it had little power to resist the development. It noted that the decision on the merits of the planning application would be determined by South Oxfordshire District Council, and that the Town Council Planning Committee, as a planning consultee, would be considering the planning application shortly.
Henley Town Council rejected the proposal from EE in July last year. In November Henley Town Council Planning Committee agreed with the proposal to install a new 5G after reviewing a pre-planning application from EE Ltd however they requested that the mast can be used to host other antennas in the future from all providers and that access is taken from the west of the site rather than crossing Makins Recreation Ground.
In the planning application it states that the new 5G 20m mast is “to address a gap in EE coverage and network capacity to the town of Henley-On-Thames whereby the existing coverage and capacity is very poor but in addition this is to replicate potentially loss of coverage from an existing EE site on St Mary’s Church which cannot be upgraded due to the nature of the roof being unable to support the upgraded equipment.” In the Design and Access Statement document accompanying the planning application it states that 35 other sites were discounted including Townlands, Henley Fire Station and Cedar House.
EE sought pre-application advice from SODC which states, “You have provided a list of the potential sites to serve the coverage requirements. I consider that some of these will need further explanation as to why they have been discounted. For example, D5 (Townlands Hospital) should be explored further in terms of the potential for the equipment to be positioned somewhere within this large site. Also, D15 (Henley Fire Station) supports existing telecommunications and this location would appear to be eminently suitable to share subject to upgrades. D17 (Cedar House) would also appear to have some potential and should not be discounted at this stage.” It also added, “The site is designated as a Local Green Space in the Joint Henley & Harpsden Neighbourhood Plan and the related Policy ENV4 states that ‘proposals for development on these Local Green Spaces will only be permitted in very special circumstances.”
Many EE and 3 Henley customers aired their frustrations on the mobile service, particularly over Henley Regatta and afterwards on Facebook Henley Community Matters.
To respond to the planning application go to https://data.southoxon.gov.uk/ccm/ Deadline for comments is 21 January 2025.











Should also be clarified that the pre application advice that they sought was not for the same location as they applied so I would question any conclusions the planning officer reached.