30 Weeks of Roadworks on the A4130 Bix Dual Carriageway

UPDATE 20 November 2014
The Bix dual carriageway road works are now complete, earlier than programmed, and the concrete width restrictors have been removed. Normal service on the A4130 has been resumed.
UPDATE 22 September 2014
Drivers who use the A4130 at Bix are still being advised to plan their journeys to avoid delays as works progress to the next stage.
Skanska have made good progress on the £4.5m resurfacing and improvement scheme and are on course to finish, as programmed, in December. The dual carriageway section of resurfacing is complete and the contractors are resurfacing and reconstructing the carriageway at the tie-in sections at Bix Village and the Fair Mile.
Both sections are being worked on simultaneously under two-way temporary traffic signals. The width restrictions at Nettlebed and the Fair Mile will remain in force during this work. Some delays may be experienced during peak traffic times and we are asking road users to plan their journeys in advance if possible and allow extra time.
During the resurfacing on the Fair Mile, the B480 Lower Assendon junction will be subject to an off-peak closure from 9am to 5pm to enable the works to be undertaken safely. The junction will be open to traffic outside of these hours.
Traffic needing access to Lower Assendon will be diverted via the B481 at Nettlebed and B480 and vice versa
UPDATE 16 June 2014
Contraflow now in operation. A4130 open to cars and light vehicles only for two way traffic travelling in contra-flow
- Vehicles wider than 2.0m that cannot use the contra-flow shall follow the diversion
- Access to Bix maintained at Rectory Lane
- Rectory Lane closed for exiting Bix; exit along Old Bix Road
- Broadplat Lane closed
Roadworks will start on the 12 May 2014 for a duration of 30 weeks on A4130 Bix Dual Carriageway.
The works include replacing and improving the existing failing drainage network, excavating the existing swallow hole and reinstating with free draining granular material, and resurfacing and reconstruction of the carriageways in both directions.
The work plan is as follows:
Enabling Works to allow for Contra-flow
- 12.05.14 – 03.06.14 proposed duration
- Closure of Henley-bound; road open Oxford-bound only
- Access to Bix maintained at Rectory Lane
- Rectory Lane closed for exiting Bix; exit along Old Bix Road
- Vehicles travelling Henley-bound must use diversion or find an alternative route
Contra-flow
- A4130 will be open to cars and light vehicles only for two way traffic travelling in contra-flow
- Vehicles wider than 2.0m that cannot use the contra-flow shall follow the diversion
- Access to Bix maintained at Rectory Lane
- Rectory Lane closed for exiting Bix; exit along Old Bix Road
- Broadplat Lane closed
Traffic Signals – Bix End
- Resurfacing work constructed under temporary signals
- Broadplat Lane closed
- Width restrictions will remain in operation
Traffic Signals – Lower Assendon End
- Resurfacing work undertaken using temporary signals
- B480 closed; vehicles must use the diversion through Nettlebed via the B481
- Width restrictions will remain in operation
Click here to download maps showing the roadworks plan.



I will be taking some friends with me on the afternoon of Monday 23rd June 2014. I drive a small/medium sized car and will be travelling from Wallingford to Henley about 2pm.
Unforunately I cannot decipher from the information given whether, although the road is closed, will a contraflow system be in operation so that we can get through?
I look forward to hearing from you.
Thank you.
Mike Sedman