Signals Mar Rail Changes

The introduction of the new rail timetable was marred earlier today when signals were set to red on the main line between Twyford and Slough, causing all services to need to pass Twyford on the single slow line and preventing trains stopping there eastbound during the morning rush hour. There was a further knock-on effect on the branch line when a driver was unable to get to Twyford to operate one of the rush hour round trips.
Problems arose soon after 7am and were not fully cleared until just before noon. Passengers who made it to Twyford were required to go to Reading to get to London, causing delays of up to an hour.
Great Western Railway and Network Rail sent this information to rail users in two updates during the morning:
“You may be aware that an axle counter failed at Slough earlier this morning, closing the mainline from Twyford through to London Paddington.
This closed the mainline from Twyford through to London Paddington for most of the morning peak, leading to a significant reduction in services for Twyford, Maidenhead, Slough, Taplow and Burnham, with some Bedwyn services terminating at Reading. Trains were very crowded as a result and customers had a long wait.
Network Rail are on site and working on a repair. It will take time to recover however and we wanted you to know what was happening.
It is of course disappointing that this should happen on the first morning of the new timetable. We are sorry for the impact on customers, and we will have it fixed as quickly as possible.”
Mike Gallop | Managing Director Western | Network Rail and Mark Hopwood | Managing Director | Great Western Railway
Local community rail group Henley Trains, which tried to guide passengers through the problems, said:
“This was a painful start to the new timetable which includes the introduction of TfL Rail services to Paddington. Axle Counters are used to ensure that a train has fully passed a location and to mark the line as clear for the next train, and are a key element of safety for travellers. We will be at Twyford with the GWR staff every evening this week to help travellers with the timetable changes, and to pick up scheduling and capacity issues.”
Henley Trains can be contacted on Twitter @Henleytrains or by email to henleytrains@gmail.com”




Follow on comment from Mark Hopwood – GWR Managing Director – on Monday evening:
Today saw the start of our new timetable; which has been 10 years in the making following major investments in brand new trains and modernised infrastructure.
This included SuperFast non stop services on some routes, improved frequency and better timing for others, and it meant thousands more seats, up to 10,000 more in the morning peak into Paddington.
Overall the timetable worked well. It wasn’t perfect as there were problems in the morning caused by failed signalling equipment on the main line into Paddington. This led to delays and cancellations. We have apologised to customers and as with any infrastructure delay we will be reviewing the root cause and the time it took to repair. It was very disappointing that this coincided with the start of the new timetable and very frustrating for our customers, some of whom faced long delays and crowded services.
However, despite the problems, the new timetable is now operational.